Electrical
Will the panel take a heat pump?
An NEC 220.82 load calc: does your service have headroom for a heat pump, or is an upgrade coming?
The dwelling
Kitchen / dining 20A circuits, minimum 2.
Nameplate watts; 0 if gas.
Dishwasher, disposal, etc; sum the nameplates.
Nameplate; amps at 240V times 240.
Service load
Calculated demand129 A/ 200 A
Fits: the service has room
Heating / cooling load
11,300 VAHeadroom
71 AUses the NEC 2023 Article 220.82 optional method for a single 120/240V dwelling service rated 100A or more; it is not valid for other configurations or for feeder/branch sizing. This is an estimate, not an engineered load calc or a code determination. A licensed electrician or the AHJ must verify the load, the panel bus and breaker capacity, and the nameplates. A pass here does not guarantee open breaker spaces or utility capacity.